top of page
Search
  • Admin

Remarkable Project Result for 6 Wrecks Removal Project

Updated: Aug 31, 2019

DB Group has completed very successful wreck removal projects for 6 ship wrecks in Middle East.


The Greatest Commitment, Delivered Beyond Goals.

Estimated Light Tons

• 6265 Ton

• 6720 Ton

• 6745 Ton

• 7688 Ton

• 5838 Ton

• 7000 Ton

Scope of Works

Survey

- Preliminary Survey

- Detailed Survey-Diving & Exterior Hull Survey

- Safety Survey (HAZARD, etc.)

Preparation & Mobilization

- Engineering & Rig up

- Sail out & Anchorage to Wreck Area - Mobilization of Salvage Vessel including

Equipment & Personnel

- Permission, Immigration and Custom Clearance

Oil Recovery

- Hot Tapping & Pump out

- Recovered Oil Transit & Disposal

- Emergency Response and Oil Spill Prevention Planning

Wreck Removal

- Wreck Area Dredging

- Inspection Diving for Grid/Cutting Section

- Removal of Crane, Foremast & Hatch cover

- Smashing Gravity Hammer for Cutting

- Recovery of Wreck Piece

- Loading Scraps to Delivery Barge


Transportation, Load Out & Disposal

- Sea Transportation for removed wrecks

- Scrap Load Out & Disposal






128 views0 comments
bottom of page